[MoRTH insights](https://indusdesk.com/morth/insights/)

# User fee reset for NH-334 Meerut-Muzaffarnagar, with 150% on bypasses

https://indusdesk.com/morth/insights/user-fee-reset-for-nh-334-meerut-muzaffarnagar-with-150-on-bypasses/

S.O. 6094(E) replaces the 2010 user fee on the four lane Meerut-Muzaffarnagar section of NH-334, with 1.5 times the base rate on 42.066 km of bypasses. The Ministry of Road Transport and Highways issued it on November 6, 2026. It applies to Meerut-Muzaffarnagar section of NH-334 (old NH-58), Uttar Pradesh, km 52.250 to km 130.560, four lanes.

MoRTH · November 6, 2026

Vishnu Gupta

The Ministry of Road Transport and Highways (MoRTH) issued notification S.O. 6094(E), dated November 6, 2026. It is published in the Gazette of India, Extraordinary, Part II, Section 3, Sub-section (ii), No. 5861, dated November 6, 2026 (CG-DL-E-10112026-277810). It is made under section 7 of the National Highways Act, 1956, read with rule 3 of the National Highways Fee (Determination of Rates and Collection) Rules, 2008. It supersedes the user fee notification S.O. 2183(E) of September 6, 2010. It is signed by Chetna Nand Singh, Joint Secretary, under F. No. DLDIV-20018/91/2025-PIU Meerut/ E-268174.

The notification recalls that S.O. 1097(E) of August 4, 2005 entrusted km 52.250 to km 131.000 of the Meerut-Muzaffarnagar section of NH-58 (new NH-334) in Uttar Pradesh to the National Highways Authority of India (NHAI). It levies the fee for use of the four lane section from km 52.250 to km 130.560 and authorizes NHAI to collect it through its officials or a contractor. The base rates per km, for the base year 2007-08, run from Rs 0.65 for a car, jeep, van or light motor vehicle to Rs 4.20 for an oversized vehicle with seven or more axles.

All of it is collected at one fee plaza, at km 75.990 of NH-334 at Shiwaya Village, Meerut district. The base rate applies to a net road length of 35.590 km. One and a half times the base rate applies to 42.066 km of bypasses, each costing Rs 10 crore or more: Meerut (18.196 km), Khatauli (8.495 km) and Muzaffarnagar (15.375 km). Seven structures longer than 60 m, 0.654 km in all, are charged at the base rate as 6.540 km of road, using an "equalisation factor" of 10. For the three half flyovers, the notification counts half the length, as if on the right-hand side only.

A person who owns a vehicle registered for non-commercial purposes and lives within twenty kilometers of the fee plaza may buy a monthly pass at Rs 360 for 2026-27, revised every year under the rules. A return trip within 24 hours costs one and a half times the one-way fee, and a pass for fifty or more single journeys in a month costs two-thirds of the fee for those journeys. Commercial vehicles registered in Meerut district, other than those under a national permit, pay 50% of the rate where no service road or alternative road is available. Overloaded vehicles pay the fee set in rule 10 of the rules.

The notification doesn't give a fee in rupees per trip, doesn't say when collection under it starts, and doesn't say how the new fee differs from the 2010 one. NHAI is to calculate the actual fee and the discounts on the basis of the completed length of the section, revise them every year under rule 5, and publish them in at least one newspaper each in English and the local language. The estimated capital cost of the project is Rs 1039.41 crore, which may change because land acquisition, utility shifting and tree cutting are yet to be completed.

**Issued by**: Ministry of Road Transport and Highways

**Document**: Notification S.O. 6094(E)

**Dated**: November 6, 2026

**Published**: Gazette of India, Extraordinary, Part II, Section 3, Sub-section (ii), No. 5861, November 6, 2026 (CG-DL-E-10112026-277810)

**Supersedes**: S.O. 2183(E), September 6, 2010

**Legal basis**: Section 7, National Highways Act, 1956; rule 3, National Highways Fee (Determination of Rates and Collection) Rules, 2008

**Applies to**: Meerut-Muzaffarnagar section of NH-334 (old NH-58), Uttar Pradesh, km 52.250 to km 130.560, four lanes

**Fee plaza**: Km 75.990 of NH-334 at Shiwaya Village, Meerut district

**Road length at base rate**: 35.590 km

**Bypasses at 1.5 times base rate**: 42.066 km: Meerut 18.196 km, Khatauli 8.495 km, Muzaffarnagar 15.375 km

**Structures over 60 m**: 0.654 km, charged as 6.540 km at the base rate

**Collected by**: National Highways Authority of India, through its officials or a contractor

**Monthly pass, local non-commercial vehicle**: Rs 360 for 2026-27, for owners living within 20 km of the plaza

**Return journey**: One and a half times the one-way fee, valid 24 hours

**Fifty single journeys**: Two-thirds of the fee for fifty or more journeys, valid one month

**Local commercial vehicles**: 50% of the rate, where no service road or alternative road is available; not for national permit vehicles

**Takes effect**: Not stated

**Estimated capital cost**: Rs 1039.41 crore, subject to variation

**Entrustment**: S.O. 1097(E), August 4, 2005, to NHAI

## Base rates in Table 1

| Type of vehicle | Base rate of fee per km, base year 2007-08 (Rs) |
|---|---|
| Car, Jeep, Van or Light Motor Vehicle | 0.65 |
| Light Commercial Vehicle, Light Goods Vehicle or Mini Bus | 1.05 |
| Bus or Truck (Two Axles) | 2.2 |
| Three-axle commercial vehicles | 2.4 |
| Heavy Construction Machinery (HCM) or Earth Moving Equipment (EME) or Multi Axle Vehicle (MAV) (four to six axles) | 3.45 |
| Oversized Vehicles (seven or more axles) | 4.20 |

[The notification](https://files.indusdesk.com/morth/notifications/2026/so-6094e.pdf) (PDF, 1.1 MB)

Source: [Gazette of India, Gazette of India, Extraordinary, Part II, Section 3, Sub-section (ii), No. 5861, November 6, 2026 (CG-DL-E-10112026-277810)](https://egazette.gov.in/WriteReadData/2026/277810.pdf).

Checked against the official copy on November 12, 2026.

- [All MoRTH insights](https://indusdesk.com/morth/insights/)